Binyah Company for Metro Station Excavation Works

Binyah Company for Metro Station Excavation Works

Project Title:

“Supply & Execute of retaining structure and dewatering system Contract-Dariya Gate Excavation for Metro-Box Works”

Client:

BINYAH (PIF)

DIRIYAH COMPANY (PIF)

Scope of Works:

Diaphragm Wall Shoring System

Anchor Shoring Support System

Dewatering

Challenges:

  • Very deep excavation up to 55 meters underground for the metro box and the high ground water table
  • Heavy equipment required to be lowered into the deep pit
  • Complex permits and environmental compliance

Mitigation:

  • Usage of diaphragm wall with multiple supporting levels and carefully designed deep well dewatering system
  • Real time monitoring for both retaining system and dewatering setup.
  • Develop precise lifting plans with high capacity cranes and utilizing backup safety systems.
  • Implement dust control, ground water reuse and vibration monitoring in line with DGDA and Saudi Vision 2030 sustainability goals.

References:

Saudi: Binyah secures $193mn Diriyah Gate Riyadh Metro excavation contract
🔗 link